FMSbonds, Inc. recently underwrote $10.793 million in special assessment revenue bonds for the Lone Tree Public Improvement District Phase #1 Project in Van Alstyne, Texas, where construction is underway on a 107-acre master-planned residential development.
Phase #1 is planned to include 185 single-family residential lots.
From Jan. 1 through Oct. 12, 2026, FMSbonds, Inc. has priced, closed or is currently marketing 66 Texas Special Assessment bond issues representing more than $865 million in bond par. Since January 2019, the firm has marketed and underwritten 405 Texas special assessment deals representing over $4.4 billion in Texas bonds, approximately 95% in market share.*
Jan. 1, 2026 – Oct. 12, 2026
Number of Texas PID Underwritings*
- FMSbonds – 66
- All Other Firms – 3
Jan. 1, 2019 – Oct. 12, 2026
Number of Texas PID Underwritings*
- FMSbonds – 405
- All Other Firms – 20
Lone Tree
The development is adjacent to Grayson College and Van Alstyne High School. Plans also include parks, open spaces, recreational trails and an amenity center.
Construction of Phase #1 improvements and major infrastructure serving the district began in October 2025. The developer expects to complete the improvements necessary for lot development in December 2026, with remaining park improvements scheduled for completion in March 2027.
Home construction in Phase #1 is expected to begin in the first quarter of 2027.
For more information, call Tripp Davenport at 214-418-1588 or email tdavenport@fmsbonds.com.
* Based on data from the Texas Municipal Advisory Council through Oct. 12, 2026, with market-share calculations performed by FMSbonds, Inc. Market share is calculated by number of qualifying Texas PID bond issues, with each issue credited entirely to its senior manager. Excludes PID bonds supported by ad valorem taxes and out-of-state conduit issuers, including Wisconsin PFAs, that were not reviewed or approved by the Texas Attorney General. Percentages may not total 100% due to rounding.
This article contains forward-looking statements regarding the project’s anticipated development, including projected lot/unit counts, home counts, construction timing, and planned amenities, which are based on the developer’s current plans and are subject to change. Actual results may differ materially due to construction delays, market conditions, financing, permitting, or other factors. This article is for informational purposes only and does not constitute an offer to sell or a solicitation to buy any securities. Any such offer is made only by the official statement, which should be reviewed in full before making any investment decision. FMSbonds, Inc. undertakes no obligation to update these statements.